Field House Steel Framing Begun

Installation has begun on the steel framing at the SOCA Belvedere Field House.  First, the light gauge steel posts and structure are being installed to create the locker rooms, meeting rooms, fitness room and trainer’s room on the field level.  The ceiling of the field level rooms will also be the floor of the main entrance level.

The massive steel framing that will enclose the field space is scheduled to begin installation next week, May 18.

The concrete crew is working their way around the building, now forming the back wall to be poured on Friday, May 15.

The overall project remains on schedule for a September opening.