SOCA Logo
SOCA Logo

News

Field House Construction Continues Progress

Construction continues on the SOCA Field House at Belvedere.  Despite frequent April showers, the project remains largely on schedule.  Concrete perimeter walls are nearing completion, with internal masonry divider walls also in progress.  Ground floor plumbing has been started, which will service the bathrooms and locker rooms used by athletes and visitors.

The huge steel framing sections are on site, with installation scheduled to begin later this week.

Project completion is expected in September.

Check here for updates, and look for the exciting photos of the steel installation coming soon!